Accelerated Urban Freeway Reconstruction:
California ¡®Rapid Rehab¡¯ Approach
Eul-Bum Lee1 and John T. Harvey2
1 Research Engineer, Institute of Transportation Studies, University of California at Berkeley.
2
Associate Professor, Dept. of Civil & Envrn. Eng., University of California at
Davis.
Abstract
Since 1998, the California Department of Transportation (Caltrans) has been
implementing the Long-Life Pavement Rehabilitation Strategies (LLPRS) program to
rebuild approximately 2,800 lane-km of high volume urban freeway with pavements
designed to last 30-plus years. This case study presents an innovative
fast-track approach applied to a heavily trafficked urban freeway reconstruction
project in Southern California. Badly deteriorated truck lanes in
both directions along a 4.5-km stretch of Interstate 15 (I-15) were rebuilt from
the gravel base up. The operations, estimated to take 10 months using
traditional nighttime closures, were completed in two continuous,
round-the-clock operations (about 9 days each, 210 hours). This paper details
the integrated approach to pavement design, construction logistics, and traffic
operations, from planning through final construction, used in the I-15 Project.
This ¡°Rapid Rehab¡± project adopted state-of-practice technologies to accelerate
construction, mitigate traffic disruptions, and propagate project information.
It shows that this method of accelerated reconstruction yielded lower road user
costs stemming from work zone traffic delay; produced longer-life pavement,
improved safety for motorists and workers, and significantly reduced
construction costs (about $6 million), compared to the traditional approach of
using repeated nighttime closures.
Keywords:
Fast-track construction; Concrete pavement; Highway reconstruction; Public
opinion; Project evaluation.